CNRL

Module Fabrication and Assembly for Kirby North 19A Tank Farm

SCOPE:
Fabrication and Assembly of 14 Modules and 4 Ship Loose Pipe packages, including Electrical, Instrumentation and Insulation

STATS:

Project Start: September 2017

Project Completion: May 2018

Duration: 7 months

Safety @ Completion: 0 First Aid / 0 LTI / 0 TRIF / 1 Medical / 1 Modified Duty / 1 Near Miss

Weld Repair Percentage @ Completion: 1.7%

Total FDI: 28,912 FDI

Total LM Pipe: 7080 LM Installed (+ Hydro of Ship Loose Pipe spools)

Total KGs Steel: 586,507 KGs Fabricated and Erected

Total EHT: 11,667 LM

Total Cable: 3081 LM (+ 2442 LM Cable Tray)

Total Insulation: 4129 LM (+ 397 soft covers)