Past Work

Case Studies

Husky Energy

Wellpads 5-8 wellpairs & CPF Facilities

SCOPE:

Wellpad: Fabrication, Assembly, E&I and Insulation of Up to 18 Modules and 1 ship loose piping package
CPF: Fabrication, Assembly, E&I and Insulation of 15 Modules and 13 ship loose piping packages

STATS:

Project Start: 2015 - Present

Project Completion: 13 Wellpad facility projects & 4 CPF Projects

Duration:
Wellpad – 3.5 Months
CPF – 8 Months

Safety @ Completion: 0 TRIF/0 LTI

Total FDI:
Wellpad:  6860.5 FDI per Wellpad 
CPF: 39,752 FDI per CPF

Total Assembly:
Wellpad: 3050 LM Pipe installed x 13 /
CPF: 3450 LM Pipe Installed x 4 + Ship loose spools hydrotested

Total Cable Tray:
Wellpad: 584 LM
CPF: 1242 LM

Total Cable Pulled:
Wellpad: 4235 LM
CPF: 2045 LM

Total EHT & Glycol trace Installed:
Wellpad: 1627 LM
CPF: 4185 LM

Total Insulation:
Wellpad: 3183LM (+ 756 Soft Covers)
CPF: 2249 LM (+ 415 Soft Covers)

Base Load of Module yard – Program to complete 4 Wellpads per year and 1 CPF Facility.

Central Processing Facilities:

Well Pads: